MODE OF PAYMENT:
9.
All demand draft shall be any
scheduled bank in favour of HP State Forest Corporation Ltd.,
and payable either at Shimla or the nearest town/city/village
where the Himkashth Sale Depot shall have the bank account. The
successful purchaser shall tender one bank draft towards sale
price payable at Shimla or the nearest town/city/village where
the Himkashth Sale Depot shall have a bank account drawn in
favour of HP State Forest Corporation Limited.
SANCTION OF BID:
10 The date of sanction will be the
date announced by the sanctioning authority on the spot or the
date mentioned in the telegram to the President of Timber
Merchant Association at Yamuna Nagar/ Pathankot as well as the
Divisional Manager/ Depot Officer concerned. Provided that such
sanction shall always be subject to condition of deposit of the
income tax due from the purchasers as per the provision of
section 44 AC read with section 206 C of Income Tax Act, 1961
along with the sale proceeds. Provided further that the deposit
of Income Tax payable by the Purchaser within the stipulated
time as aforesaid, shall be a condition precedent to the sale
and failure to do so shall be deemed to constitute retraction of
the bid by the bidder and make him to liable the forfeiture of
earnest money deposit and give the Corporation the right to
re-auction the resiled lots afresh.
11. PAYMENT OF THE
PURCHASE PRICE TIME OF PAYMENT;
11.1 The purchaser (s) shall pay
the price of timber purchased within 55
days of sanction as
stated in para 10 above and shall also lift the
entire timber sold to
him /them within this period of 55 days.
11.2 Director (marketing) may under
exceptional circumstances and on
application by the purchaser (s)
allow and extension in making the
payment up to 30 days as he
considerers fit on the payment of interest
@ of 27% P.A. on the belated
amount in the manner prescribed for
making the payment.
11.2 (a) Beyond the period specified in
11.2 Executive Director may give
extension in period of payment
on payment of interest @ 2.5 % p.M.
on belated payment.
PART PAYMENT AND REMOVAL:
11.3 While applying for extension under
clause 11.2 the purchaser will deposit 10% of the total sale
value of the timber purchased by him with the concerned
Divisional Manager to qualify for extension beyond 55 days. The
Divisional Manager may recommend the extension with 27% interest
on the belated sale amount in the manner prescribed for making
payment. This 10 % security amount will be adjusted against
the value of the total timber purchased by the bidder at the
time of making final payment of the timber purchased. However,
if he fails to make the payment within the extended period, the
amounts so deposited by him will be forfeited to the Corporation
and no further extension will be granted.
11.4 If the entire payment of the sold lot
of timber is make within 45 days from the effective date of
sanction, the rebate will be allowed following rates:-
REBATE;
1 If payment is made within 15
days = 5%
2. If payment is made within 30
days = 4%
3.If payment is made within 45
days = 3%
MODE OF PAYMENT:
11.5 Payment of sale price within
the period of 55 days shall be made by crossed demand drafts
only drawn as stated in para supra.
GRACE PERIOD:
11.6.1
In case of payment by demand draft
as stated in para 11.4a grace period of 3 days will be allowed
for receipt of the drafts at Sale Depots, provided the date of
issue of the demand draft is within the period specified above.
In case the last day on which any payment is to be made to the
Corporation is a holiday either in the Himkashth Sate Depot of
the Corporation or in the Banks in HP Punjab and Haryana then
the date shall automatically stand extended to the next working
day.
ADJUSTMENT OF EMD:
11.7 The earnest money deposit for a
particulars lot will be adjusted only when the final payment of
the lot is made by the purchaser in the period mentioned above.
FAILURE TO PAY:
11.8 In case any purchaser fail
to pay the whole or in part the price for the
sold lot within the
prescribed time of 55 days as stated in sale
condition 11.1 above and the
timber is not lifted by the party within the
stipulated period as well as
within extended period covered under the
sale condition NO. 12.3 and 12.4.
the entire earnest money or purchase price received shall be
forfeited and the Corporation shall have the right to resale the
timber.
12
EXTENTION TIME
FOR LIFTING:
12.1 The purchased timber shall be
lifted only against a release permit issued
by the Depot Officer.
PERIOD FOR LIFTING:
12.2 The purchaser shall lift the purchase
timber within 55 days from the date of sanction. However, if
after full payment of the lot has been made
and the entire quantity can not be
lifted for want of Truck load, such timber may be allowed to be
kept in the Depot upto the 20 days after the date of next
auction without any Depot rent. The quantity which may be
detained under this concession will not be exceed 8m3. In case
the purchaser fails to lift this timber within the period
specified above, depot rent as provided herein after shall by
payable from the date of expiry 55 days from the date of
sanction in respect of that lot.
EXTENSION OF 30 DAYS:
12.3 The Divisional Manager or Depot
Officer may allow extension upto 30 days beyond the time
specified for lifting in clause in 12.2 above on payment of
Depot rent @ 22% P.A on pro rate value of timber and unlifted.
FURTHER EXTENSION:
12.4 The Director (Marketing) may under
exceptional circumstances and on an application by the purchaser
allow a further extension for 30 days or payment of Depot rent @
22% P.A. on the pro rata value of un-lifted timber. Director
(Marketing) may give further extension on charging depot rent @
3% per month. No extension will be granting in respect of C
Class timber beyond the period as mentioned in condition 12.3.
STACKING:
12.5 All timber as per para 12.2 to 12.4
at the discretion of the Depot Officer/ Divisional Manager will
be removed and stacked in a separate portion of the depot at the
cost of purchaser. Such cost will be deposited in cash before
the issue of the release order by the Depot Officer/ Divisional
Manager.
PALTAI:
13
Paltai of timber of the sold lot
may be allowed to the purchaser provided this is done in the
presence of Divisional Manager/ Depot Officer and no disturbance
is caused to the adjoining stacks and the full payment of the
stacks in question has been made.
RESTRICTION OF SALE ETC.:
14
No purchaser shall sell timber
purchased by him to another party while such timber is lying in
the Corporation depot. No sawing or conversion of timber is to
be permitted in the depot premises under any circumstances what
so ever.
CONDITION FOR REMOVAL:
15
No timber shall be allowed to be
removed from the sale Depot without the issue of proper release
order to be issued by the Depot Officer as per Corporation rules
and without timber having been marked with export sale
hammer and presentation of the release order, challan and Gate
pass as per Corporation Rules& Regulation in force from time to
time.
ARBITRATION:
16
All or any dispute arising out of
the auction sale of interpretation of any
of the sale condition
contained herein shall be referred to the Managing Director, HP
State Forest Corporation Limited and his decision shall be final
and binding on the purchaser.
JURISDICTION:
17. Court proceeding if any
connected with the sale shall be subject to the
jurisdiction of Himachal
Pradesh Courts only.
18. The auction sale in HSDs are
subject to such restriction as may be
imposed by the Govt. of H.P.
from time to time.
19. These conditions of sale shall
also from the terms of the Agreement
Deed between the seller
(HPSFC) on the one side and buyer on other
side.
AUCTIONING AUTHORITY
Certified
that I/We heard/read and understood the above conditions of sale
in respect of timber put to auction as announced on the day
time and timber and place mentioned above and sign with my/our
own hand(s) in acceptance thereof and will abide by these.
|
Sr.No.
|
Name &
Address of the purchaser(S) |
Signature
|
|
1 |
2 |
3 |
|